Progress Update

by Tudor Marici on February 02, 2023

This is an exciting time in the construction of the new Student Building. We are working on many projects simultaneously. Last week we finished polishing the floors, painted the ceilings, and completed the framing.

Currently, we are focusing on installing the drywall and prepping for paint. We will paint the inside of the building first and then get started on the outside.

Construction Site Feb 1

Over the next two weeks, we will continue to have a lot of small interconnected details running simultaneously. These details need to run smoothly, with little to no margin for error. We ask that you would continue praying for God's hand over everyone working on the project, the deadlines, and the inspections.

How you can pray specifically for this project:

  1. For us to meet the deadlines and pass the inspections smoothly and quickly.
  2. Safety for workers.
  3. For the families and students who will be able to use the building. That the remodeled student space would be a place for many students to come to know Jesus and learn to walk with him.